Reed Contact
Jason Henning
Reed Division
Civil
Project Location
Erina, NSW 2250
Project Client
RTA of NSW
Project Engineer
SKM on behalf of the RTA
Project Start Date
29-09-2005
Duration of Construction
65 weeks
Project Value
$9 Million (inclusive of GST)
Contract Type
GC21 Edition 1 (RTA)
Duplication of 650m of carriageway from 2 to 4 lanes along The Entrance Road, including the construction of road pavements, bridgeworks, retaining walls, service utility relocations and property adjustments.
High volumes of traffic, sporadic inclement weather, service adjustments, access to neighbouring properties.
Reviewing and amending structure designs to ensure constructability.
Close monitoring of Hubbards Creek which runs adjacent to much of the project to insure minimal disruption.
Reed Constructions opened the project to four lanes of traffic, including all access roads and side streets in mid-August 2007. The remaining property and services adjustments were undertaken and completed in mid-September 2007. Despite numerous challenges, Reed Constructions has successfully delivered a significant infrastructure towards the Central Coast Highway Upgrade.