Reed Project
Auburn Railway Bridge and Intersection Upgrade
Reed Contact
Victor Ng
Reed Division
Civil
Project Location
Auburn, NSW 2144
Project Client
Auburn Council
Current Status
100% complete
Project Start Date
28-06-2004
Duration of Construction
26 weeks
Hydraulical Engineer
Connell Wagner
Project Overview
Demolition and replacement of an existing rail overbridge with a new five lane wide single span bridge structure including widening and raising South Parade and Rawson St.
Project Value
$11.4 Million (Inclusive of GST)
Contract Type
GC 21 (Amended Design & Construct)
Project Map