Reed Project |
Club Burwood |
Progress |
Sydney’s latest club and nightspot was handed over in late September and has opened to the public. This three storey building, on Sydney’s Burwood Road is easily identified by its electric purple paint work. The complete internal refit is no less striking – with the interior featuring wood, vinyl and tile walls along with a stunning neon water feature. Patrons can enjoy gaming, bar and function facilities in a location where no expense has been spared. |
Reed Contact |
Malcolm Clements |
Reed Division |
Hospitality |
Project Location |
Burwood, NSW 2134 |
Project Client |
Burwood RSL |
Current Status |
100% complete |
Project Start Date |
01-02-2006 |
Duration of Construction |
26 weeks |
Architect |
Wood + Day Patnership |
Engineer |
Norman Disney Young |
Other Consultants |
Cardno Young |
Project Overview |
Complete demolition of all internal services and finishes. Construction of new lift shaft and internal staircase. Also being constructed are 4 new bar areas and 2 new kitchens complete with new services including toilets, cool rooms, and offices. New gaming rooms and function facilities are also being added to modernise the club. |
Project Challenges |
Some challenges facing the Reeds during the construction of this project are the structural changes required to the building along with the new lift shaft and internal staircase. The project is also being constructed over multiple levels. |
Is Reed Doing Anything Specific To Meet Client's Needs? |
Reeds have closely liaised with architect and client to overcome existing building issues. |
Project Value |
$4.6 Million (inclusive of GST) |
Contract Type |
Lump Sum |
Project Map |
|