Reed Project |
North West Growth Centre First Release Precincts Package One Works |
Progress |
Reservoir and pipeline construction works to service future residential development in Sydney’s North West have commenced in Rouse Hill and Kellyville. Reservoir site construction commenced in August 2009, and the installation of potable water, recycled water and sewer commenced in November 2009.The design of the remaining water infrastructure is near completion with construction of potable water pipelines associated with the reservoir to commence in April 2010. Weather permitting, the works will be completed by late 2010. |
Reed Contact |
Tom Burns |
Reed Division |
Water |
Project Location |
Rouse Hill, NSW |
Project Client |
Sydney Water, Principal: Australian Water (No. 1) Pty Ltd |
Current Status |
60% complete |
Project Start Date |
12-11-2008 |
Duration of Construction |
104 weeks |
Structural Engineer |
MAUNSELL AUSTRALIA / SAUNDERS INTERNATIONAL |
Electrical Engineer |
THOMPSON CONTROLS |
Mechanical Engineer |
MAUNSELL AUSTRALIA |
Hydraulical Engineer |
MAUNSELL AUSTRALIA |
Project Overview |
The first release of the North West Growth Centre covers North Kellyville, Riverstone, Alex Avenue, Riverstone West and Area 20 precincts. The project involves the design and construction of a potable water surface reservoir, trunk potable water inlet and outlet mains, potable water and recycled water distribution mains, reservoir site mains and gravity sewer carriers. |
Project Challenges |
Liaison with relevant stakeholders and management of concept and detailed design process to enable construction works to be commenced at the earliest opportunity. |
Is Reed Doing Anything Specific To Meet Client's Needs? |
With a project of this magnitude, The Reed Group will be constructing infrastructure within established communities, including residences, businesses, schools, sports fields, public spaces and roads. Community relations is integral to project management supporting successful project outcomes. |
Project Value |
$75 million (inclusive of GST) |
Contract Type |
GC21 (AS AMENDED by Sydney Water Corporation) |
Any specific OH&S or environmental issues |
Environmental issues include the management of threatened and protected species of flora and fauna as well as management of Indigenous and European heritage. OH&S risks include working adjacent to creeks and waterways, trafficable roads and within private properties. |