Reed Project |
Bootawa Dam Water Treatment Plant |
Reed Contact |
Chad Wilkinson |
Reed Division |
Water |
Project Location |
Bootawa Dam Road off Bootawa Road, 8 km West of Taree, NSW |
Project Client |
Midcoast Water |
Current Status |
100% complete |
Project Start Date |
20-03-2007 |
Duration of Construction |
118 weeks |
Project Overview |
This project involves the construction of all civil works on the site, including earthworks, reservoirs, tanks, buildings for the treatment unit, the amenities/control area, chemical dosing equipment and the main pumping stations, which includes roads, drainage, site service, etc. It involves design, construction, installation and commissioning of the equipment for Bootawa Water Treatment Plant for the Manning District Water Supply. There are also associated electrical and mechanical installations. The new water treatment plant will have an initial capacity of 60ML per day and provisions to upgrade to 75ML per day in the future. |
Project Value |
$49.5 Million (inclusive of GST) |
Contract Type |
AS 2124-1986 (AS AMENDED) |
Project Profile PDF |
|
Project Map |
|