Reed Project |
Queanbeyan Hospital Redevelopment |
Progress |
The new hospital car park was handed to the client on March 13 2009, and is now in use. The finalisation of the 102 space car park completes the hospital redevelopment, with the new hospital having been completed in November and opened in December 2008. |
Reed Contact |
Mark Ardouin |
Reed Division |
Health |
Project Location |
Queanbeyan, NSW 2620 |
Project Client |
NSW Department of Health (NSW Health Admin Corp) |
Current Status |
100% complete |
Project Start Date |
21-12-2006 |
Duration of Construction |
108 weeks |
Architect |
Suters Architects |
Structural Engineer |
Hughes Trueman |
Electrical Engineer |
Jim Hatz and Associates |
Mechanical Engineer |
Erbas and Associates |
Hydraulical Engineer |
Acor Consultants |
Other Consultants |
BCA Consultant - Trevor Howes & Assoc |
Project Overview |
Design and construction of integrated hospital facility, including demolition, bulk excavation, temporary services to provide the facilities for 55 beds, clinical support, community and ambulatory health facilities, modification of an existing building, and new carpark. |
Project Value |
$45.4 Million (inclusive of GST) |
Contract Type |
HGC21 |
Project Profile PDF |
|
Project Map |
|