Reed Project
Stockland Merrylands Carpark
Progress
Work on the second and third stages of the new multi-level car park are complete, with handover due in late June. The first stage of the new parking facility was completed last year and has been in use by shoppers for the past eight months.
Reed Contact
Marcus Moscos
Reed Division
Construction
Project Location
Merrylands, NSW 2160
Project Client
Stockland Development Pty Ltd
Current Status
100% complete
Project Start Date
29-10-2007
Duration of Construction
77 weeks
Architect
Group GSA Pty. Ltd.
Structural Engineer
TTW Pty. Ltd.
Electrical Engineer
Waterman AHW Pty. Ltd.
Hydraulical Engineer
GJ Sparks and Partners Pty. Ltd.
Other Consultants
Civil Engineer: TTW Pty. Ltd.
Project Overview
Construction of 5 Level concrete carpark. This multi-level car park adjoining the shopping centre sits on 26,000sqm of prime retail land and will be directly linked to two customer shopping entry points. The remaining levels will be accessed via two lifts to aid pedestrian traffic flow.
Project Challenges
Very limited access. Working adjacent Merrylands Retail building site – 2 building sites within one development.
Is Reed Doing Anything Specific To Meet Client's Needs?
Staging of the works in accordance with the Client’s needs and requirements.
Project Value
$42.2 Million (inclusive of GST)
Contract Type
Amended Form of AS4300 – 1995 Design and Construct Contract (Non-Residential) (NSW)
Any specific OH&S or environmental issues
Portions of the excavation will be within an old tip site – environmental management.