Reed Project
Wollongong Northern Distributor Extension
Reed Contact
Matthew Quinn
Reed Division
Civil
Project Location
Woonona, NSW 2517
Project Client
Roads and Traffic Authority of New South Wales
Current Status
100% complete
Project Start Date
28-12-2006
Duration of Construction
110 weeks
Project Overview
Construction of new four lane extension of WNDE, including major earthworks, soil nailing, shotcreting, construction of 12 road bridges, and a pedestrian bridge, stormwater and sub surface drainage, reinforced concrete and reinforced soil retaining walls, asphalt and heavily bound pavement courses, noise barriers and miscellaneous works.
Project Value
$88 Million (inclusive of GST)
Contract Type
GC21 (Edition 1) RTA