Reed Project
McKell Building Toilet refurbishment
Progress
Nineteen floors of new amenities for the McKell Building have been completed, with the final seven floors commissioned in mid-November.
Reed Contact
Malcolm Clements
Reed Division
Interiors
Project Location
2-24 Rawson Place Sydney
Project Client
NSW Department of Commerce
Current Status
100% complete
Project Start Date
20-12-2006
Duration of Construction
29 weeks
Architect
Govenment Architects
Engineer
Govenment Architects
Structural Engineer
Govenment Architects
Electrical Engineer
Govenment Architects
Mechanical Engineer
Govenment Architects
Hydraulical Engineer
Govenment Architects
Project Overview
Refurbishment of 12 floors of existing toilet facilites. With the construction of new disabled toilets to each floor. Complete renewel of all surfaces and fixtures to create new toilet areas for the Department of Commerce staff.
Project Challenges
The major challenge for this project is the work taken place in premises that are currently occupied along with part of the works requiring completion throughout the night over a four staged program to reduce interruptions with employees.
Is Reed Doing Anything Specific To Meet Client's Needs?
The client required a prototype floor to be created on the first level with regular inspections being carried out over the first stage to ensure client approval with the finishes and overall look and feel along with usability of the facilities.
Project Value
$1.8 Million (inclusive of GST)
Contract Type
GC21