Reed Project
Concord Repatriation Hospital
Progress
After final commissioning the Concord Repatriation Hospital was formally handed over in the first week of March, six months ahead of schedule. The facility was opened opened to the public in April/May after staff recruitment and training.
Reed Contact
Tony Fletcher
Reed Division
Health
Project Location
Concord, NSW 2139
Project Client
Sydney South West Area Health
Current Status
100% complete
Project Start Date
31-05-2006
Duration of Construction
91 weeks
Architect
Woods Bagot
Other Consultants
Civil Engineer: Aurecon
Project Overview
The Construction of a new Mental Health Facility located on approximately 5.4 hectares of the Concord Repatriation General Hospital. The facility includes the construction of twelve new structures to accommodate a range of mental health treatments including Rehabilitation, Intensive Psychiatric care, Acute Psycho-geriatric care and an administration section.
Project Challenges
A major challenge for this project is that the Head Contract does not have a ‘traditional’ RFI Information System but instead a ‘Contractor Proposal’ (CP) System. Under this Information System RCA have had to identify, formulate and propose solutions in to design and site issues and to make submissions to the Principal’s Authorized Person.
Is Reed Doing Anything Specific To Meet Client's Needs?
Reed’s project team suggested and implemented an alternate wall system of hebel panels instead of the specified brickwork in certain areas of the buildings to enable cost savings to be achieved. RCA also conduct fortnightly meetings with the Clients representatives to ensure all of the Client’s needs are being met.
Project Value
$52.7 Million (inclusive of GST)
Contract Type
GC21
Project Profile PDF
PDF Project Profile