Reed Project
Mudgee-Gulgong Water Treatment Plant
Reed Division
Water
Project Location
Mudgee, NSW 2850
Project Client
Department of Commerce
Current Status
100% complete
Project Start Date
31-03-2003
Duration of Construction
78 weeks
Architect
Department of Commerce
Engineer
Demlakian & Associates
Hydraulical Engineer
Hunter Water Australia Pty Limited
Project Overview
Construction of two water treatment plants, two river intake pump stations, a booster pump station and associated works.
Project Value
$15.15 Million (Inclusive of GST)
Contract Type
AS2124 - 1986 (as amended)