Project Facts


Reed Contact

Mark Ardouin

Reed Division

Health

Project Location

Randwick, NSW

Project Client

Healthscope

Project Engineer

Umow Lai

Project Start Date

TBA

Duration of Construction

Stage 1 - 4 weeks, Stage 2 - 20 weeks

Contract Type

AS2164 with special conditions


Prince of Wales Private Hospital Theatre Redevelopment (Stage 1 and 2)

Stage 1 involves the construction of new offices, reception, tea room and recovery areas. The works involved in Stage 2 are construction of two new operating theatres, scrub rooms anaesthetics bays, staff station, 17 bed recovery bay CSSD upgrade and new change rooms.

Challenges

Staged project working within a fully functioning hospital environment including working close to operating theatres and managing patient flows.

Clients Specific Needs

Detailed review with the client on patient flows to allow seamless installation of temporary hoardings and early involvement with the designers to achieve cost savings to offset variation costs. To minimise noise and vibration concerns, drilling into the concrete slabs changed from percussion drilling to core drilling to allow installation of structural steel components. Early identification of services shut downs to limit the impact on the hospital.

Any specific OH & S or environmental issues

Close attention to noise and dust control.