Project Facts


Reed Contact

Tom Burns

Reed Division

Water

Project Location

Rouse Hill, NSW

Project Client

Sydney Water, Principal: Australian Water (No. 1) Pty Ltd

Project Start Date

12-11-2008

Duration of Construction

104 weeks

Project Value

$75 million (inclusive of GST)

Contract Type

GC21 (AS AMENDED by Sydney Water Corporation)


North West Growth Centre First Release Precincts Package One Works

The first release of the North West Growth Centre covers North Kellyville, Riverstone, Alex Avenue, Riverstone West and Area 20 precincts. The project involves the design and construction of a potable water surface reservoir, trunk potable water inlet and outlet mains, potable water and recycled water distribution mains, reservoir site mains and gravity sewer carriers.

Challenges

Liaison with relevant stakeholders and management of concept and detailed design process to enable construction works to be commenced at the earliest opportunity.

Clients Specific Needs

With a project of this magnitude, The Reed Group will be constructing infrastructure within established communities, including residences, businesses, schools, sports fields, public spaces and roads. Community relations is integral to project management supporting successful project outcomes.

Any specific OH & S or environmental issues

Environmental issues include the management of threatened and protected species of flora and fauna as well as management of Indigenous and European heritage. OH&S risks include working adjacent to creeks and waterways, trafficable roads and within private properties.