Filter Results by:
Division:
State:





Project Facts


Reed Contact

Malcolm Clements

Reed Division

Interiors

Project Location

2-24 Rawson Place Sydney

Project Client

NSW Department of Commerce

Project Engineer

Govenment Architects

Project Start Date

20-12-2006

Duration of Construction

29 weeks

Project Value

$1.8 Million (inclusive of GST)

Contract Type

GC21


McKell Building Toilet refurbishment

Refurbishment of 12 floors of existing toilet facilites. With the construction of new disabled toilets to each floor. Complete renewel of all surfaces and fixtures to create new toilet areas for the Department of Commerce staff.

Challenges

The major challenge for this project is the work taken place in premises that are currently occupied along with part of the works requiring completion throughout the night over a four staged program to reduce interruptions with employees.

Clients Specific Needs

The client required a prototype floor to be created on the first level with regular inspections being carried out over the first stage to ensure client approval with the finishes and overall look and feel along with usability of the facilities.

Progress

Nineteen floors of new amenities for the McKell Building have been completed, with the final seven floors commissioned in mid-November.