Reed Contact
Michael Hughes
Reed Division
Construction
Project Location
Lismore, NSW 2480
Project Client
Department of Commerce
Project Start Date
28-07-2006
Duration of Construction
93 weeks
Project Value
$11.4 Million (including GST)
Contract Type
GC21
Design and construct a new 3 level police station and refurbishment of existing heritage police building to service the Lismore command area with more than 140 police. Construction to include 6 new holding cells, police training facilities along with an underground interlink with neighbouring courthouse.
There are approx. 8 stages within the construction program that will require relocation management and working around fully operating police station.
At this stage of the project Reed are working with the designers to ensure all clients requirements are met.