04-08-2006

Duration of Construction

28 weeks

Project Value

$5.3 Million (inclusive of GST)

Contract Type

GC21


Hornsby Ku-ring-gai Hospital Mental Health Intensive Care

Construction of a single storey, 12 bed, in-patient, intensive care mental health unit, car parking and landscaping.

Challenges

Constructing a building to meet all Hospital demands from its quality of finish and complexity of services and equipment covering many functions from straightforward office areas through to an intensive care unit.

Clients Specific Needs

The main aim of providing a quality facility with minimal disruption to the existing Hospital was achieved through co-operation and effective communication, from the whole project team involved in this redevelopment.

Any specific OH & S or environmental issues

Excavation through existing hospital grounds requiring specific attention to minimise disturbances to hospital staff and patients and the removal of selected trees adjacent existing buildings.