Project Facts


Reed Contact

Tony Fletcher

Reed Division

Health

Project Location

Concord, NSW 2139

Project Client

Sydney South West Area Health

Project Start Date

31-05-2006

Duration of Construction

91 weeks

Project Value

$52.7 Million (inclusive of GST)

Contract Type

GC21


Concord Repatriation Hospital

The Construction of a new Mental Health Facility located on approximately 5.4 hectares of the Concord Repatriation General Hospital. The facility includes the construction of twelve new structures to accommodate a range of mental health treatments including Rehabilitation, Intensive Psychiatric care, Acute Psycho-geriatric care and an administration section.

Progress

After final commissioning the Concord Repatriation Hospital was formally handed over in the first week of March, six months ahead of schedule. The facility was opened opened to the public in April/May after staff recruitment and training.