Reed Contact
Eleo Estacio
Reed Division
Civil
Project Location
Cameby Downs, QLD
Project Client
Syntech Resources Pty Ltd
Project Engineer
Matthew Palmer Consulting Engineers P/L
Project Start Date
09-05-2010
Duration of Construction
11 weeks
Project Value
$15 Million (Inclusive of GST)
Contract Type
Alliance
Six kilometers of earthworks and embankment construction, complete with verge and capping layers, ready for Queensland Rail for laying of ballast and rail on 27 July 2010. This project also includes drainage works consisting of two box culverts and six pipe culverts, maintenance access road, earth swales, fencing and batter protection works.
Lack of local materials which satisfy Queensland Rail specifications, relocation of Telstra services, and working under the strict Queensland Coal Mines Act and Regulations.
Importation and delivery of imported material on a 24-hr operation is the only way to meet material requirements in a tight schedule. Telstra relocation was fast tracked by seeking assistance from Telstra to award relocation works as soon as possible. All site staff are working under strict induction, safety standard operating procedures and constant vigilance with regards to safety.
The project is governed by the Queensland Mines Act and Regulations.